Disruption unavoidable says manager as Nenagh works carried out

Date:

Share:

From next Monday, construction is set to ramp up as gas, water and sewerage lines are being laid from the bottom of Kenyon Street. 

The work, which will lead to traffic diversions and closures, will last for the next 12 months as the contractors make their way up through the North Tipp town. 

- Advertisement -

The carpark at the Railway station will be free of charge for the duration of the works to ease congestion.

Construction Manager with Gas Networks Ireland Brendan McDermott says it's impossible to carry out a project of this size without disruption.

Business representatives in Nenagh say they're concerned Phase three of the gas project will lead to job losses. 

advertisement

New book on Tipperary hurling launches this week

A new book on Tipperary hurling launches this week. Tipperary - Land of Blue...

Thurles CBS advance to final eight, Nenagh’s Harty Cup defence...

Thurles CBS are into the quarter-finals of the Dr. Harty Cup. The Mid Tipp...

Tipperary woman honoured by Munster GAA

One of the main meeting rooms in Áras Mumham was renamed in honour...

Three Tipp schools in Harty Cup action this afternoon

The knockout stages of the Harty Cup get underway today. Three Tipperary teams are...
advertisement

Tipp Today Full Show 041224

On wednesday's Tipp Today, Fran spoke to newly elected Tipp TD Ryan O'Meara...

TT Gardening – 041224

Our Gardening expert Ultan Nesbitt was on hand to answer all your gardening...

The Land of Blue and Gold – Stephen Gleeson

Our own Stephen Gleeson has released his latest book. Land of the Blue and...
advertisement