Road works on Davitt Street in Tipperary town are well on track according to council officials.

The work is being done in 10 phases, with 5 on each side of the road.

- Advertisement -

The first two phases – which is from the Tesco entrance to Pierse Motors on both sides of the road – have been completed.

The third phase has commenced, which is from Beechgrove Garden centre to Pierse Motors – with the fourth stage to be completed by the end of May.

Louise Farrell, resident engineer on the N24 project on Davitt St, explains the next steps.

advertisement

Jockey remains in ICU following Thurles fall

Jockey Michael O'Sullivan is in intensive care at Cork University Hospital after his...

Tipp look to continue winning start to National Hurling League

Tipperary go up against Limerick in the National Hurling League this weekend. The Premier...

Bennett hitting form in France

Tipperary’s Sam Bennett notched up a top 10 finish on Stage 2 of...

Thurles Racing abandoned after jockey injured in fall

This afternoon's (Thursday) card at Thurles had to be abandoned after a jockey...
advertisement

Ar An Lá Seo 7-2-25

Fáilte ar ais chuig eagrán nua de Ar An Lá Seo ar an...

Tipp Today-The GAA Catfish- with Leanne

The most recent installment of the 2 Johnnie's GAA Catfish has taken Ireland...

Tipp Today – Friday Panel- 07/02/25

Our Friday Panel is unpacking the hot topics of the week... Tipp FM Radio...
advertisement