Nenagh works nearly at an end

Photo © Tipperary Co Co

The €17 million Ervia gas, water and wastewater project in Nenagh is nearing completion.

The construction element of the project is due to be finished this month, while all road closures are due to be lifted by December.

The project involves the laying of over 40km of gas pipelines, alongside 4.2km of water mains and 1.7km of wastewater mains.

The work is nearing completion with the gas and water elements of the project due to be finished by the end of the month.

Work to replace the water main in Rossa Place is still due to be carried out, along with the replacement of numerous lead service connections located on Bulfin Rd and Conlan’s Rd.

This will be the final construction element of the work.

Road reinstatement got underway at the end of July and will continue through to the end of November.

The resurfacing works have been co-ordinated with Tipperary County Council’s programme of works to reinstate kerbs and footpaths on the same roads.

All of the works are due to be completed by December.